Lion Stadium Track & Field

Kaufman ISD

Project Scope

  • Removal of existing track and events
  • Excavation and compaction for proper density and moisture
  • Chemical injection
  • Installation of drainage system, concrete curbs, and asphalt
  • Application of PTS 2000 spray coat system
  • Synthetic turf field installed in 2019

Products

  • Paragon Track Surfaces 2000 spray coat system
  • Turf: Shaw Sports Turf Legion NXT
  • Infill: Sand/rubber

01 / 01

  • “Paragon Sports Constructors, whether they are part of the team at the beginning or are awarded the project through competitive bidding, comes to the table as a team player, with the interest of the school district and a successful project in mind. Their professionalism and impeccable service along with their construction expertise has contributed directly to the success of many athletic building projects.”


    Jeramy Burleson | Kaufman ISD Athletic Director/Head Football Coach